To set up Budget Production Quantity imports to Foundation, you will need to follow the below steps:

Create DataGenie Importer for J/C Budgets

If you have not yet set up a Data Genie for Imports in Foundation:

  1. From the Foundation homepage, go to Genies --> Import:

Homepage

  1. In the ImportGenies window, select J/C BudgetGenie and then OK:

Homepage

  1. Select J/C Budget Only.

  2. Select the following columns and press Add->. Make sure to select they are lined up vertical in the below order:

    • Cost Code No
    • Job No
    • Original Quantity
    • Phase No
    • Unit of Measure

Homepage

  1. Once you are finished adding columns, select Next>> at the bottom.

  2. Add a memorable name (e.g. Budget Quantity Import). Then, for Update Bid Amt, select No. Then press Finish:

Homepage

Import Budgets into Foundation

Let's say I want to export the below Budget Production Quantities to Foundation from my Project Management system:

Homepage

  1. After exporting a Budget Production Quantity from Procore, you should receive an email with a CSV file that you can import to Foundation. Open the email and download the file to your downloads folder:

Homepage

  1. Go to the Foundation homepage and select Job Costing:

Homepage

  1. Under Daily, select Import Estimates:

Homepage

  1. Under the Criteria tab:
  • For Import Title, select the DataGenie you created for Budget Production Quantity Imports.
  • For Estimate Filename, select the filepath for the CSV file you downloaded from the email in step 1 above. If you downloaded the file to your Downloads folder, the filepath is likely "M:\Users\Your PC Name\Downloads\date-BPQ-Import.csv (e.g. "M:\Users\John\Downloads\2024-10-31-BPQ-Import.csv").
  • For Import File Type, select "Comma Separated".

Homepage

  1. Select the Report tab. An import will now begin. If the import is successful, you will see a message like the below:

Homepage

  1. To confirm the Budget Production Quantities imported successfully, go to the Budgets tab for the Job you imported the Budget (Estimate) to. It will include the estimate details you just imported:

Homepage

  1. If I press "Refresh Data" in the Agave Sync UI, the two Budget Production Quantities will automatically link to the imported Budget Quantities: