To set up Budget Production Quantity imports to Foundation, you will need to follow the below steps:
Create DataGenie Importer for J/C Budgets
If you have not yet set up a Data Genie for Imports in Foundation:
- From the Foundation homepage, go to Genies --> Import:
- In the ImportGenies window, select J/C BudgetGenie and then OK:
-
Select J/C Budget Only.
-
Select the following columns and press Add->. Make sure to select they are lined up vertical in the below order:
- Cost Code No
- Job No
- Original Quantity
- Phase No
- Unit of Measure
-
Once you are finished adding columns, select Next>> at the bottom.
-
Add a memorable name (e.g. Budget Quantity Import). Then, for Update Bid Amt, select No. Then press Finish:
Import Budgets into Foundation
Let's say I want to export the below Budget Production Quantities to Foundation from my Project Management system:
- After exporting a Budget Production Quantity from Procore, you should receive an email with a CSV file that you can import to Foundation. Open the email and download the file to your downloads folder:
- Go to the Foundation homepage and select Job Costing:
- Under Daily, select Import Estimates:
- Under the Criteria tab:
- For Import Title, select the DataGenie you created for Budget Production Quantity Imports.
- For Estimate Filename, select the filepath for the CSV file you downloaded from the email in step 1 above. If you downloaded the file to your Downloads folder, the filepath is likely "M:\Users\Your PC Name\Downloads\date-BPQ-Import.csv (e.g. "M:\Users\John\Downloads\2024-10-31-BPQ-Import.csv").
- For Import File Type, select "Comma Separated".
- Select the Report tab. An import will now begin. If the import is successful, you will see a message like the below:
- To confirm the Budget Production Quantities imported successfully, go to the Budgets tab for the Job you imported the Budget (Estimate) to. It will include the estimate details you just imported:
- If I press "Refresh Data" in the Agave Sync UI, the two Budget Production Quantities will automatically link to the imported Budget Quantities: