Autodesk Build: Contract Type Mapping not Setup

Symptoms

When pushing Change Orders, you get the error message [Autodesk Build] Validation Errors: The contract type field is required.

Causes

The Change Order Types in Autodesk Build do not match the Change Order types in Sage 100C.

How to fix

To enable a seamless sync of Change Orders from Autodesk to Sage 100 Contractor, you will want to enable a mapping of Change Order Types between Autodesk Build and Sage 100C.

To enable this mapping:

  1. In Autodesk Build, from Cost, go to Settings-->Change Order-->Change Order Types.
  2. In Sage 100 Contractor, go to a Change Order, and select the arrow next to Type to open the list of valid Change Order Types.
  3. Add the list of Change Orders types in Autodesk Build to Sage 100 Contractor.