Skip to main content

Budget changes must have a balance of zero when the net-zero setting is enabled. Please adjust the amounts

Symptoms

When pushing a Budget Transfer to Procore, you get the error message: [Procore Error] Budget changes must have a balance of zero when the net-zero setting is enabled. Please adjust the amounts..

Causes

This error appears because the budget transfer you're trying to push does not have a balance of zero while your Procore project is configured to require net-zero budget changes.

How to fix

To resolve this error, you can either:

  1. Change your budget transfer to be net zero:
  • In the source system, adjust your budget transfer so that it's net zero (i.e., the transfer isn't increasing or decreasing the total value of your budget)
  1. Adjust your settings in Procore to allow non net-zero budget changes
  • In Procore, go to Project Tools > Budget > Budget Settings
  • Uncheck the "Require net zero Budget Change amounts" box
  • Retry syncing

Still having trouble?

Contact Agave Support or your account manager for help.